Grants and outside funding items in Town of Morrisville, between 27 Nov 2025 and 27 Nov 2026
4 items. Each one links to the meeting it was on. This is the bottom of every drill-down on this site: whatever a chart says, the items behind it are here to be counted.
Search and filter
What these items are about
The subjects carried by every item this filter selects, not just the ones shown below. Each one narrows the list further.
Show these numbers as a table
| Subject | Items |
|---|---|
| Grants and outside funding | 4 |
| Contracts and procurement | 2 |
| Budget and appropriations | 1 |
| Economic development incentives | 1 |
| Stormwater and flooding | 1 |
-
Would let the town manager sign a construction contract with Blum Construction for up to $4 million to rebuild the cricket field with six pitches and an underdrain, and move $1 million from the Parks Capital Reserve Fund to cover the overrun. Held over from October 13; staff make no recommendation and offer approval,…Resolution and capital project ordinance amendment approved, both unanimous
-
Listed under New Items, not consent. Authorizes the construction phase with Blum Construction, not to exceed $4 million, $1 million over budget, with the gap moved from the Parks Capital Reserve Fund. The field gets an underdrain system and six pitches in place of four; a $2 million Wake County hospitality tax grant s…No vote; deferred to October 27 for more information (per the recording)
-
Staff or committee report Grants and outside funding
-
A hearing and a vote the same night on an economic incentive grant agreement with Novartis Innovative Technologies. The packet carries both an original agreement and an updated one.
Download these items as CSV Where else this comes up
Follow this
These links carry the filters above. Put one in a feed reader or a calendar and it keeps answering the same question as new meetings are collected — no account, and nothing about you is stored.