Planning Board Special Meeting
Chatham County ·
Planning Board
Tuesday, July 14, 2026 at 6:30 pm · Emergency Operations Center, 112 Innovation Way Pittsboro, North Carolina 27312
Agenda document Minutes Meeting page Watch Meeting recap
What's on this agenda
Chatham County's Planning Board spent 14 July on the technical limits it might write into data center rules: noise, vibration and light, heat emissions, generators and back-up power, and water use. Staff opened with the timeline for the moratorium the commissioners adopted on 11 February and a legal review, and the vice chair introduced each subject in turn.
Summarized from the published agenda. Read the agenda itself before acting on it.
Meeting recap
What happened, drawn from the records published after the meeting. Minutes
The board did not settle the noise question. A motion to leave the dBA standards as the county's noise ordinance already writes them failed 2-7. The chair argued for a clear infrasound standard measured at the property line, as the dBA limit is, and the vice chair agreed that dBC and possibly dBG need limits of their own but at different numbers, because each weighting scale measures something different.
Public comment pushed further than the board's remit. One speaker asked the board to recommend prohibiting data centers outright rather than writing zoning rules for them. Staff reminded the board twice of its limits: it can only recommend, and any change it proposes to the noise ordinance would have to apply to every industry in the county rather than to one use.
How the votes went
The agenda was approved 8-0. The motion to leave the dBA noise standards as written in the county ordinance failed 2-7.
From the published minutes.
Speaking at this meeting
Chatham County's own rules for public comment — check them before you rely on anything here.
Agenda items (9)
-
III Approval of AgendaProceduralApproved 8-0
-
IV Framing the DiscussionDiscussion item Data centers and large loads
-
V Staff Presentation: next steps and timeline for the moratorium, legal reviewStaff set out two timelines, a longer one finishing recommendations for potential approval in January and a shorter one, and reviewed the legal constraints.
-
VI Public Input SessionPublic hearing Data centers and large loadsSpeakers asked the board to recommend prohibiting data centers outright rather than regulating them.
-
VII.1 Board Discussion: NoiseWhether to write new noise limits for data centers or keep the county's existing ordinance, and how to handle low-frequency sound and infrasound.A motion to leave the dBA standards as written failed 2-7
-
VII.2 Board Discussion: Vibration and Light
-
VII.3 Board Discussion: Heat Emissions
-
VII.4 Board Discussion: Generators and Back-up powerBack-up generators, including how many hours a year they run and what tier of diesel engine they use.
-
VII.5 Board Discussion: Water Use