| Stormwater and flooding | 3 |
| Contracts and procurement | 1 |
| Environment and sustainability | 1 |
| Fees and utility rates | 1 |
| Intergovernmental agreements | 1 |
| Water and sewer | 1 |
-
A design-build contract to Edifice Construction for the Fleming Loop Park turf renovation, which addresses persistent drainage problems so fields can be played on after heavy rain. The park stays open during construction: the left side closes for three months, then work moves to fields 4 through 7.
-
Agreement with the state sedimentation control commission updating erosion and sedimentation control delegation.
-
Staff reviewed CIP projects, rate models, an interbasin transfer update, and stormwater-permit-driven investment needs, raising a stormwater utility fee or a tax increase as funding options.